development project. Its goal was to develop a software to automate medical
insurance quotes. It was scheduled as a six-month project and should be ready
by January 1, 1995, when Giga Safe’s new rates were to be released. However,
although the project started with a highly motivated team and high expectations,
it missed all deadlines and was not completed until May 1995.
To sum things up, the project failed mostly because of bad scheduling and
planning, as well as insufficient management control and decreasing team
morale. With a more structured approach to project management and better
planning the project could have been completed in a shorter time.